Environmental Management Plan (EMP) and Reports (EMR)
 

Following completion and approval of the Environmental Assessment for the wharf expansion, a Environmental Management Plan (EMP) was submitted to the Ministry of Environment and Climate Change (MOECC) for approval. The EMP was accepted by MOECC on May 12, 2017.
 

The EMP for Phase 1 of the wharf expansion documents the environmental protection, mitigation measures and commitments made in the EA proccess. It also specifies the details fo monitoring and compliance measures during the construction and operation phases of the project.
 

The EMP and acceptance letter are available for viewing below:

 

Environmental Management Reports (EMR)

The EMR reports are completed following each construction season and are submitted to the Ministry of Environment, Conservation and Parks (MECP) for review. The completed reports are available for review below: